VTrans Construction Updates

Richmond – Bolton

U.S. Route 2 Rehabilitation

 

DATE: September 21, 2023

TRAFFIC IMPACT: Traffic Control with one-lane of alternating travel motorists can expect moderate traffic delays during all working hours. PLEASE slow down and follow the posted speed limits.

PROJECT UPDATE: Completed installation of the second lift of pavement between Baker Street and the I-89 Exit 11 interchange. Began driveway tie-ins within the Richmond Village; Continued adjusting the sewer structures to pavement grade within the Richmond Village.

CONSTRUCTION ACTIVITIES:

The following is the anticipated work schedule for the week beginning September 24, 2023:

Sunday through Friday – 7:00 p.m. to 6:30 a.m.:

  • Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
  • Continue ditching and shoulder work between Baker Street and the I-89 Exit 11 interchange.

Monday Through Friday – 6:30 a.m. to 6:30 p.m.:

  • Weather permitting, continue the final lift of paving at the eastern end of the project between Cochran Road and Lemroy Court.
  • Weather permitting, continue paving the second lift of pavement from Kenyon Road to the Richmond/Williston town line.
  • Continue driveway tie-ins from the eastern end of the project in Bolton to Lemroy Court.
  • Continue shoulder work throughout the project limits.

PLEASE USE CAUTION AND FOLLOW THE POSTED SPEED LIMITS!

 

Final paving began this morning on the east end of the project in Bolton, working westerly

 

SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference US-2 Richmond, if you would like to received weekly project updates via email.

COMPLETION DATE:  July 2024

Contact Information:

Name – Stephanie Barrett – Public Information Consultant

Phone – 802-399-7847

Email – sbarrett@coibsinc.com

 
Visit the Project Website
 

Richmond

US Route 2 Bridge #29 Replacement

 

DATE: September 21, 2023

TRAFFIC IMPACT:

  • U.S. Route 2 – Traffic control will be present allowing for 1-lane of alternating travel.
  • Monday through Friday I-89 both southbound and northbound passing lanes will be closed from 5:30 a.m. to 3:00 p.m. and both the southbound and northbound right shoulders will be closed all within the project.

PROJECT UPDATE: Placed concrete for the pier wall; Continued support of excavation on the east side of the bridge for abutment #2; Continued installing fill in front of the Richmond Fire Station.

CONSTRUCTION ACTIVITIES:

The following is the anticipated work schedule for the week beginning September 21, 2023:

Monday through Friday 6:30 a.m. to 6:00 p.m.:

  • Begin forming and tying rebar for the backwall of Abutment #2.
  • Continue support of excavation on the east side of the bridge for abutment #2 work.
  • Continue installing fill in front of the Richmond Fire Station to build up the ground.

PLEASE USE CAUTION AND FOLLOW THE POSTED SPEED LIMITS!

 

Placement of concrete for the I-89 median bridge pier

 

PROJECT TYPE: Complete bridge replacement

 

SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference Bridge#29, Richmond, if you would like to received weekly project updates via email.

COMPLETION DATE: September 2025

Contact Information:

Name – Stephanie Barrett – Public Information Consultant

Phone – 802-399-7847

Email – sbarrett@coibsinc.com

 
Visit the Project Website
 
 

Contact

Email: clerkbolton@gmavt.net